Commitments to unrealistic time and resource estimates may result in____________________?
(A) project delay
(B) poor quality work
(C) project failure
(D) all of the mentioned
Which of the following is not a project manager’s activity ?
(A) project control
(B) project management
(C) project planning
(D) project design
Who delivers the technical skills that are necessary to engineer a product or an application ?
(A) Practitioners
(B) Project managers
(C) Senior managers
(D) None of the mentioned
Which of the following is a people-intensive activity ?
(A) Problem solving
(B) Organization
(C) Motivation
(D) Project management
Which of the following term is best defined by the statement “The creation of a new codeline from a version in an existing codeline” ?
(A) Branching
(B) Merging
(C) Codeline
(D) Mainline
Which activity sits at the core of software requirements analysis ?
(A) Problem decomposition
(B) Partitioning
(C) Problem elaboration
(D) All of the mentioned
What assess the risk and your plans for risk mitigation and revise these when you learn more about the risk ?
(A) Risk monitoring
(B) Risk planning
(C) Risk analysis
(D) Risk identification
Risk management is one of the most important jobs for a__________________?
(A) Client
(B) Investor
(C) Production team
(D) Project manager
Which of the following term is best defined by the statement: “The underlying technology on which the system is built is superseded by new technology.” ?
(A) Technology change
(B) Product competition
(C) Requirements change
(D) None of the mentioned
Which of the following risks are derived from the organizational environment where the software is being developed ?
(A) People risks
(B) Technology risks
(C) Estimation risks
(D) Organizational risks