Which of the following is a project scheduling method that can be applied to software development ?
(A) PERT
(B) CPM
(C) CMM
(D) Both PERT and CPM
What is used to determine the recommended degree of rigor with which the software process should be applied on a project ?
(A) Degree of Rigor
(B) Adaptation criteria
(C) Task Set
(D) Both degree of Rigor and adaptation criteria
A technique for performing quantitative analysis of progress is known as______________________?
(A) BCWS
(B) EVA
(C) BAC
(D) CBSE
Which of the following is not an adaptation criteria for software projects ?
(A) Size of the project
(B) Customers Complaints
(C) Project staff
(D) Mission criticality
An example of a system that may use a process pipeline is a high-speed_________________?
(A) data distributing system
(B) data acquisition system
(C) data collector system
(D) none of the mentioned
Which of these following sensor is a useful as part of a burglar alarm system for commercial buildings ?
(A) Movement detector
(B) Door sensor
(C) Window sensor
(D) All of the mentioned
Which of the following is not real-time architectural patterns that are commonly used ?
(A) Asynchronous communication
(B) Observe and React
(C) Environmental Control
(D) Process Pipeline
The UML was designed for describing _______________________?
(A) object-oriented systems
(B) architectural design
(C) SRS
(D) Both object-oriented systems and Architectural design
Which of the following is an architectural conflict ?
(A) Using large-grain components improves performance but reduces maintainability
(B) Introducing redundant data improves availability but makes security more difficult
(C) Localizing safety-related features usually means more communication so degraded performance
(D) All of the mentioned
What describes how a set of interacting components can share data ?
(A) model-view-controller
(B) architecture pattern
(C) repository pattern
(D) none of the mentioned