Crash project duration is obtained by summing the________________?

(A) normal durations for all the activities

(B) crash durations for all activities

(C) crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

(D) crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities