Civil Engineering Mcqs

In “full face” method of constructing tunnels, the first operation relates to______________?

(A) removal of bottom portion

(B) excavation of one drift in the centre

(C) removal of top portion

(D) excavation being done along the periphery

Submitted By: Ali Uppal