The constraints in case of resource smoothening operation would be_______________?
(A) resources
(B) project duration time
(C) both resources and project duration time
(D) none of the above
Share this... |
Facebook
|
Twitter
|
Linkedin
|
Whatsapp
|
Your email address will not be published. Required fields are marked *