Which of the following is a weakness of bar chart ?
(A) interdependencies of activities
(B) project progress
(C) uncertainties
(D) all of the above
Share this... |
Facebook
|
Twitter
|
Linkedin
|
Whatsapp
|
Your email address will not be published. Required fields are marked *