If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good______________________?
(A) EF=ES+D
(B) LS=LF-D
(C) LF = LS + D
(D) D = EF-ES
(E) all of the above