Pick up the correct step used for scheduling a project by C.P.M.__________________?
(A) a project is divided into various activities
(B) required time for each activity is established
(C) sequence of various activities is made according to their importance
(D) network is drawn by connecting the activities and the events
(E) all of the above
Share this... |
Facebook
|
Twitter
|
Linkedin
|
Whatsapp
|
Your email address will not be published. Required fields are marked *