Slack represents the difference between the___________________?
(A) latest allowable time and the normal expected time
(B) latest allowable time and the earliest expected time
(C) proposed allowable time and the earliest expected time
(D) normal allowable time and the latest expected time
(E) project initiation tune and actual starting time