The assumption in PERT is__________________?

(A) a project will always be behind schedule, if left uncorrected

(B) cost of project will always be more than the estimated cost, if no timely corrections are taken

(C) a project can be subdivided into a set of predictable, independent activities

(D) activities are fixed and can’t be changed ,

(E) commissioning time can be changed, if activities are behind schedule

Submitted By: Ali Uppal