The disadvantage of product layout is_________________?
(A) high initial investment for the specialized facilities
(B) skilled labour to operate machines
(C) production time is longer, requiring more goods in inventory
(D) high cost of inspection
(D) costly and complex production control
Routing assists engineers in deciding in advance___________________?
(A) the flow of material in the plant
(B) the methods of proper utilization of manpower
(C) the methods of proper utilization of machines
(D) the layout of factory facilities
(D) normal route of workers through the plant
A dummy activity________________?
(A) is artificially introduced
(B) is represented by a dotted line
(C) does not require any time
(D) all of the above
(D) none of the above
The difference between the time available to do the job and the time required to do the job, is known as_________________?
(A) event
(B) float
(C) duration
(D) constraint
(D) none of the above
The probability distribution of project completion in PERT follows following distribution_________________?
(A) normal
(B) binomial
(C) beta
(D) exponential
(D) Gaussian
The critical activity has____________________?
(A) maximum float
(B) minimum float
(C) zero float,
(D) average float
(D) none of these
The critical path of a network represents_______________________?
(A) the minimum time required for completion of project
(B) the maximum time required for completion of project
(C) maximum cost required for completion of project
(D) minimum cost required for completion of project
(D) none of the above
Critical path moves along the activities having total float of_____________________?
(A) positive value
(B) negative value
(C) zero value
(D) same value
(D) none of the above
Replacement studies are made on the fol-lowing basis_________________?
(A) annual cost method
(B) rate of return method
(C) total life average method
(D) present worth method
(D) any one of the above
Bin card is used in__________________?
(A) administrative wing
(B) workshop
(C) foundry shop
(D) stores
(D) assembly shop