Critical Path Net Work helps an engineer_________________?

(A) to concentrate his attention on critical activities

(B) to divert the resources from non-critical advanced activities to critical activities

(C) to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

(D) all of the above

(D) none of the above

Submitted By: Ali Uppal


Submitted By: Ali Uppal


If TL is the largest allowable event occurrence time, total activity slack (s) is equal to__________________?

(A) latest start time – earliest start time

(B) latest finish time – earliest finish time (EFT)

(C) TL-EFT

(D) all of the above

(D) none of the above

Submitted By: Ali Uppal


Submitted By: Ali Uppal


Submitted By: Ali Uppal


Submitted By: Ali Uppal


The performance of a specific task in CPM is known as ______________________?

(A) dummy

(B) event

(C) activity

(D) contract

(D) none of the above

Submitted By: Ali Uppal


Emergency rush order can be pushed more effectively in__________________?

(A) job production

(B) automatic production

(C) continuous production

(D) intermittent production

(D) none of the above

Submitted By: Ali Uppal


In a PERT chart___________________?

(A) all activities should be numbered

(B) only important activities should be numbered

(C) only critical activities are numbered

(D) only selected activities are numbered

(D) no activity is numbered

Submitted By: Ali Uppal


In PERT analysis, critical path is obtained by joining events having___________________?

(A) +ve slack

(B) -ve slack

(C) zero sldck

(D) dummy activities

(D) critical activities

Submitted By: Ali Uppal