The expected out turn of cement concrete 1 : 2 : 4 per mason per day is_________________?
(A) 1.5 m 3
(B) 2.5 m3
(C) 3.5 m3
(D) 5.0 m3
As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken________________?
(A) 1.80 litres for 5 to 10 users
(B) 1.20 litres for 15 users
(C) 1.35 for 20 users
(D) All the above
The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as_______________?
(A) Excavation
(B) Surface dressing
(C) Cutting
(D) Surface excavation
The cross -section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is__________________?
(A) b – rd)²/(r – s)
(B) b – rd)²/(r + s)
(C) ½ × (b + rd)²/(r – s)
(D) b – rd)²/(s – r)
For the construction of buildings, the subheads of the estimate are________________?
(A) Earthwork, Concrete work, Brick work
(B) Brickwork, Stone work, Roofing
(C) Brickwork Flooring, Wood work, Steel work
(D) All the above
Cost of fittings and their fixing is specified for the following sanitary fittings________________?
(A) Water closets
(B) Flushing pipes
(C) Lavatory basins
(D) All the above
The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is__________________?
(A) (6 + 15) chains
(B) (6 + 12) chains
(C) (6 + 18) chains
(D) None of these
The item of the brick structure measured in sq.m, is___________________?
(A) Reinforced brick work
(B) Broken glass coping
(C) Brick edging
(D) Brick work in arches
According to ISI method of measurement, the order of the sequence is_________________?
(A) Length, breadth, height
(B) Breadth, length, height
(C) Height, length, breadth
(D) None of these
The most reliable estimate is_________________?
(A) Detailed estimate
(B) Preliminary estimate
(C) Plinth area estimate
(D) Cube rate estimate