While preparing a detailed estimate__________________?

(A) Dimension should be measured correct to 0.01 m

(B) Area should be measured correct to 0.01 sqm

(C) Volume should be measured correct to 0.01 cum

(D) All the above

Submitted By: Ali Uppal


Submitted By: Ali Uppal


Submitted By: Ali Uppal


The measurement is not made in square metres in case of________________?

(A) D.P.C. (Damp proof course)

(B) Form works

(C) Concrete Jeffries

(D) R.

Submitted By: Ali Uppal


Submitted By: Ali Uppal


The trap which is provided to disconnect the house drain from the street sewer is called_________________?

(A) Master trap

(B) Intercepting trap

(C) Interception manhole

(D) All the above

Submitted By: Ali Uppal


The ‘centre line method’ is specially adopted for estimating_________________?

(A) Circular buildings

(B) Hexagonal buildings

(C) Octagonal buildings

(D) All the above

Submitted By: Ali Uppal


The inspection pit or chamber is a manhole provided in a base drainage system________________?

(A) At every change of direction

(B) At every change of gradient

(C) At every 30 m intervals

(D) All the above

Submitted By: Ali Uppal


In case of laying gullies, siphons, intercepting traps, the cost includes_______________?

(A) Setting and laying

(B) Bed concreting

(C) Connection to drains

(D) All of these

Submitted By: Ali Uppal


Carpet area does not include the area of_________________?

(A) The walls along with doors and other openings

(B) Bath room and lavatory

(C) Kitchen and pantry

(D) All the above